Seattle Public Utilities - GCCM Opportunity
PW# 2012-020A Landsburg Facilities & Chlorination GC/CM Preconstruction & Construction Services.
The project delivery method for the Project is General Contractor/Construction Management (GC/CM) as defined in Revised Code of Washington (RCW) 39.10.340 -.410. The GC/CM will work with SPU and the Designer (KPG) to provide constructability reviews and develop site-specific work plans.
The estimated range of construction cost is $5M-6M.
Project inquiries should be in writing and directed to: Daniel Enrico P.E. Project Supervisor daniel.enrico@seattle.gov phone: 206-684-7413 OR Kay Yesuwan P.E. Project Manager kay.yesuwan@seattle.gov Phone: 206-615-1612
Schedule of Events Target Date
RFQPA Release: October 2012
Pre-Proposal Conference and Site Visit: October 2012
Proposal Deadline: November 2012